Project Timeline
July 2022
Project Kickoff
Brings Owner’s Representative, CGL, on board to aid the County in decision making and planning for the new Lancaster County Correctional Facility.
Q3 - Q4 2022
Needs Assessment
Aids in decision making for long-term capacity requirements by taking into account industry norms and county-specific information.
Q3 2022 - Q1 2024
Programming
Defines project goals and defines types and square footage of spaces in the new facility.
Q1 – Q3 2023
Design Team Services Procurement
Selects the most qualified design team through the County’s procurement process.
Q3 2023 – Q2 2025
Design
Creates a full site, interior and exterior design for the facility.
Q3 2025
Bidding
Selects the contractor to oversee construction of the LCCF.
Q4 2025
Groundbreaking
Marks the official start of construction.
Q4 2027